Woodlawn Lane Water Main & Sanitary Force Main Upgrade Project Update

Upgrade to Route 101 – Upgrading Phase 3
July 8, 2019
Monthly Council meeting – July 17, 2019
July 16, 2019

The contractor has installed approximately 130 meters of water main and sanitary sewer force main during the second week. They are expecting to complete the installation of water main and force main by Friday, July 12th. Pressure testing of the mains is also expected to be completed. Connecting the new water main to the water system will take place next week as well as the sanitary force main will be connected to the sanitary system. Connecting homes to the new water main will follow. The project is currently on schedule. LMS