Alban Street Water, Sewer & Roadway Upgrade Update

Bears in the Village
May 11, 2020
Canadian Red Cross “Friendly Calls” program
June 16, 2020

Alban Street Water, Sewer and Roadway Upgrading Project Update:
The project commenced on Monday, May 25th. The bulk of tree removal has been completed with just a few trees left to be removed once construction approaches those areas.

The storm water structure at the Daniel Drive intersection has been installed as well as approximately 30m of storm, sanitary, and water mains. One service connection has been completed which is now running on the new storm and sanitary lines.
The entire project will be completed prior to anyone accessing the municipal water system, which will allow time for a plumber to prepare for the switch and decommissioning of the existing well.

Canada Post mailboxes have temporarily been relocated from the front corner of 12 Alban Street to the back corner of the same property but on Charters Avenue. Canada Post has informed residents of this change.